Annexation Phase V – Project 2 – LaGrange2

 

Project Details Downloads
Estimated Start: August 2007 Project Map (PDF)
Estimated Completion: Completed Construction Schedule
Estimated Cost: $2,424,505
Served: 309
Engineer Design Firm: Moorman, Kizer & Reitzel, Inc.
Construction: ES&J Enterprises, Inc (Autryville)
Search Installation by Street

 

LaGrange There are 3 phases to construction: 1) street cutting and sewer installation; 2) street repair; and 3) restoration.
Street Name EstimatedConstructionDate Status
September 2007 Fire Hydrants Installed
There are 3 phases to construction: 1) street cutting and sewer installation; 2) street repair; and 3) restoration.
Morganton Road bore at Golf Drive October 2007 Restoration Completed
Paddlewheel Outfall Restoration Completed
Paddlewheel Drive (175-198) Restoration Completed
There are 3 phases to construction: 1) street cutting and sewer installation; 2) street repair; and 3) restoration.
Paddlewheel Drive (201-214) November 2007 Restoration Completed
Paddlewheel Drive (218-230) Restoration Completed
There are 3 phases to construction: 1) street cutting and sewer installation; 2) street repair; and 3) restoration.
Grist Mill Road (6500-6537) December 2007 Restoration Completed
Cross Bow Court Restoration Completed
There are 3 phases to construction: 1) street cutting and sewer installation; 2) street repair; and 3) restoration.
Bonnie Bell Lane (6504-6518) January 2008 Restoration Completed
Golf Drive (134-108) Restoration Completed
Gatepost Court Restoration Completed
Brocton Drive (110-175) Restoration Completed
Tampico Court Restoration Completed
There are 3 phases to construction: 1) street cutting and sewer installation; 2) street repair; and 3) restoration.
108 Golf Drive to 105 Brocton Drive February 2008 Restoration Completed
Bonnie Bell Lane (6532-6519) Restoration Completed
Kemper Court Restoration Completed
Pierron Drive (200-205) Restoration Completed
Cissna Drive Restoration Completed
There are 3 phases to construction: 1) street cutting and sewer installation; 2) street repair; and 3) restoration.
Grist Mill Road (6561-6552) March 2008 Restoration Completed
Pierron Drive (200-209) Restoration Completed
Keeler Drive Restoration Completed
Lovington Drive Restoration Completed
Delliert Court Restoration Completed
Acus Court Restoration Completed
There are 3 phases to construction: 1) street cutting and sewer installation; 2) street repair; and 3) restoration.
Keeler Court April 2008 Restoration Completed
Pierron Drive (252-264) Restoration Completed