Phase 5 Annexation - Installation Timeline


Project 1
LaGrange, east of Reilly Road; Aaron Lakes, east of Bingham Drive; Shenandoah
Services
Estimated Start
Estimated Completion
Estimated Cost
1,117
April 2007
April 2009
$11 million


Project 2
LaGrange, west of Reilly Road; Arran Hills and Arran Park

Services
Estimated Start
Estimated Completion
Estimated Cost
1,028
tba
tba
$13.4 million

Project 3
Summerhill and Roundtree; Southgate; North Plymouth Street, east of Cape Fear River
Services
Estimated Start
Estimated Completion
Estimated Cost
947
tba
tba
$10 million


Project 4
Shadowlawn, Shenandoah North; Green Briar Lake, McArthur Road/Ramsey Street
Services
Estimated Start
Estimated Completion
Estimated Cost
909
tba
tba
$9.5 million


Project 5
Cliffdale West, Woodmark, Cliffdale Estates; Rayconda, Wells Place, Montibello
Services
Estimated Start
Estimated Completion
Estimated Cost
1,062
tba
tba
$12.1 million


Project 6
Northwood Estates, Raynor Drive, Village Hills, Lake Rime Estates: Carver Falls Road, Ramsey Street
Services
Estimated Start
Estimated Completion
Estimated Cost
798
tba
tba
$10 million


Project 7
Fairfield, Kingswood, Porter Place; Arran Lakes West
Services
Estimated Start
Estimated Completion
Estimated Cost
1,031
tba
tba
$11 million

Project 8
Blue Springs Woods, Lake Point, Farrington, Tunbridge, Wendover

Services
Estimated Start
Estimated Completion
Estimated Cost
1,106
tba
tba
$15.2 million

Project 9
Remaining areas in western Fayetteville

Services
Estimated Start
Estimated Completion
Estimated Cost
158
tba
tba
$1.9 million