Phase
5 Annexation - Installation Timeline
|
Project
1
LaGrange, east of Reilly Road; Aaron Lakes, east of Bingham Drive; Shenandoah
|
Services
|
Estimated
Start
|
Estimated
Completion
|
Estimated
Cost
|
|
1,117
|
April
2007
|
April
2009
|
$11
million
|
Project 2
LaGrange, west of Reilly Road; Arran Hills and Arran Park
|
Services
|
Estimated
Start
|
Estimated
Completion
|
Estimated
Cost
|
|
1,028
|
tba
|
tba
|
$13.4
million
|
Project
3
Summerhill and Roundtree; Southgate; North Plymouth Street, east of Cape
Fear River
|
Services
|
Estimated
Start
|
Estimated
Completion
|
Estimated
Cost
|
|
947
|
tba
|
tba
|
$10
million
|
Project 4
Shadowlawn, Shenandoah North; Green Briar Lake, McArthur Road/Ramsey Street
|
Services
|
Estimated
Start
|
Estimated
Completion
|
Estimated
Cost
|
|
909
|
tba
|
tba
|
$9.5
million
|
Project 5
Cliffdale West, Woodmark, Cliffdale Estates; Rayconda, Wells Place, Montibello
|
Services
|
Estimated
Start
|
Estimated
Completion
|
Estimated
Cost
|
|
1,062
|
tba
|
tba
|
$12.1
million
|
Project 6
Northwood Estates, Raynor Drive, Village Hills, Lake Rime Estates: Carver
Falls Road, Ramsey Street
|
Services
|
Estimated
Start
|
Estimated
Completion
|
Estimated
Cost
|
|
798
|
tba
|
tba
|
$10
million
|
Project 7
Fairfield, Kingswood, Porter Place; Arran Lakes West
|
Services
|
Estimated
Start
|
Estimated
Completion
|
Estimated
Cost |
|
1,031
|
tba
|
tba
|
$11
million
|
Project
8
Blue Springs Woods, Lake Point, Farrington, Tunbridge, Wendover
|
Services
|
Estimated
Start
|
Estimated
Completion
|
Estimated
Cost
|
|
1,106
|
tba
|
tba
|
$15.2
million
|
Project
9
Remaining areas in western Fayetteville
|
Services
|
Estimated
Start
|
Estimated
Completion
|
Estimated
Cost
|
|
158
|
tba
|
tba
|
$1.9
million
|