Phase
5 Annexation -
Project 5 Arran Lakes East Side updated 12/8/09 |
Served |
Estimated
Start |
Estimated
Completion |
Estimated
Cost |
209 |
October 2008 |
Completed |
$1,838,777 |
Engineer
Design Firm: |
McKim
& Creed, P.A. |
Construction: |
Triangle Grading and Paving |
Arran Lakes East Side Project Map (PDF Document)
The installation of all of the pipe in Arran Lakes East has been completed. Work continues on the final surface restoration and final closeout of the project. Connection notices have been mailed.