Phase
5 Annexation -
Project 1 Area 1A Brentwood updated 2/14/08 |
Served |
Estimated
Start |
Estimated
Completion |
Estimated
Cost |
143 |
July
2007 |
Completed |
$1,108,009 |
Engineer
Design Firm: |
McKim
& Creed, P.A. |
Construction: |
ES&J
Enterprises, Inc (Autryville) |
View
Area 1A Brentwood Project Map (PDF Document)
Installation
of sanitary sewer in the Brentwood area began the week of July 9, 2007.
PWC has contracted with ES&J Enterprises, Inc. of Autryville to install
sanitary sewer services to over 500 residents in this area. The estimated
completion of this project is December 2007.
| Brentwood
Construction Schedule There are 3 phases to construction: 1) street cutting and sewer installation; 2) street repair; and 3) restoration. |
||
| Street Name | Estimated Construction Date |
Status |
| McDougal Drive (5962-5952) | July 2007 | Restoration Completed |
| McDougal Easement | Restoration Completed | |
| McDougal Drive (6022-5962) | Restoration Completed | |
| Thatford Court | Restoration Completed | |
| Manor Haven Court | Restoration Completed | |
| There
are 3 phases to construction: 1) street cutting and sewer installation;
2) street repair; and 3) restoration. |
||
| McDougal Drive (6022-6217) | August 2007 | Restoration Completed |
| There
are 3 phases to construction: 1) street cutting and sewer installation;
2) street repair; and 3) restoration. |
||
| Arberdale Easement | September 2007 | Restoration Completed |
| Arberdale Drive | Restoration Completed | |
| East Darrow Drive (6201-6208) | Restoration Completed | |
| There
are 3 phases to construction: 1) street cutting and sewer installation;
2) street repair; and 3) restoration. |
||
| West Darrow Drive (6303-6304) | October 2007 | Restoration Completed |
| Revere Street (1088-1015) | Restoration Completed | |
| There
are 3 phases to construction: 1) street cutting and sewer installation;
2) street repair; and 3) restoration. |
||
| Wildwood Dr. & Easement | November 2007 | Restoration Completed |
| Lunar Drive | Restoration Completed | |
| Valhalla Court | Restoration Completed | |
| There
are 3 phases to construction: 1) street cutting and sewer installation;
2) street repair; and 3) restoration. |
||
| Bingham Place | December 2007 | Restoration Completed |
| Bingham Drive Easement (1030-1120) | Restoration Completed | |