Phase 5 Annexation - Project 1
Area 2C
LaGrange #2

updated 7/16/08

LaGrange #2
Served
Estimated Start
Estimated Completion
Estimated Cost
309
August 2007
Completed
$2,424,505

 

 

Engineer Design Firm:
Moorman, Kizer & Reitzel, Inc.
Construction:
ES&J Enterprises, Inc (Autryville)

View Area LaGrange Project Map (PDF Document)

Installation of sanitary sewer services in the LaGrange and Morganton Place neighborhoods began the week of August 20, 2007. The work area falls west of Reilly Road and south of Cliffbourne Dr. and Jennings Dr. and has been divided into 2 projects.

Work on the western side of the project area (west of Lovington Dr., Keller Dr., and Golf Dr.) will install 169 sanitary sewer services and is scheduled to begin in September 2007. PWC has contracted with Autry Grading to install the utilities and work is expected to be complete in June 2008.

PWC has contracted with ES&J Enterprises, Inc. of Autryville to install sanitary sewer services to approximately 300 residents on the eastern side of project area, or areas east of Lovington Dr., Keller Dr., and Golf Dr. Work in this area began in August 2007 and is estimated to be complete in May 2008.

LaGrange #2 Construction Schedule
There are 3 phases to construction: 1) street cutting and sewer installation; 2) street repair; and 3) restoration.
Street Name Estimated
Construction
Date
Status
  September 2007 Fire Hydrants Installed
There are 3 phases to construction: 1) street cutting and sewer installation; 2) street repair; and 3) restoration.
Morganton Road bore at Golf Drive October 2007 Restoration Completed
Paddlewheel Outfall   Restoration Completed
Paddlewheel Drive (175-198) Restoration Completed
There are 3 phases to construction: 1) street cutting and sewer installation; 2) street repair; and 3) restoration.
Paddlewheel Drive (201-214) November 2007 Restoration Completed
Paddlewheel Drive (218-230)   Restoration Completed
There are 3 phases to construction: 1) street cutting and sewer installation; 2) street repair; and 3) restoration.
Grist Mill Road (6500-6537) December 2007 Restoration Completed
Cross Bow Court Restoration Completed
There are 3 phases to construction: 1) street cutting and sewer installation; 2) street repair; and 3) restoration.
Bonnie Bell Lane (6504-6518) January 2008 Restoration Completed
Golf Drive (134-108)   Restoration Completed
Gatepost Court   Restoration Completed
Brocton Drive (110-175) Restoration Completed
Tampico Court   Restoration Completed
There are 3 phases to construction: 1) street cutting and sewer installation; 2) street repair; and 3) restoration.
108 Golf Drive to 105 Brocton Drive February 2008 Restoration Completed
Bonnie Bell Lane (6532-6519) Restoration Completed
Kemper Court   Restoration Completed
Pierron Drive (200-205)   Restoration Completed
Cissna Drive Restoration Completed
There are 3 phases to construction: 1) street cutting and sewer installation; 2) street repair; and 3) restoration.
Grist Mill Road (6561-6552) March 2008 Restoration Completed
Pierron Drive (200-209)   Restoration Completed
Keeler Drive   Restoration Completed
Lovington Drive Restoration Completed
Delliert Court Restoration Completed
Acus Court   Restoration Completed
There are 3 phases to construction: 1) street cutting and sewer installation; 2) street repair; and 3) restoration.
Keeler Court April 2008 Restoration Completed
Pierron Drive (252-264)   Restoration Completed