Phase
5 Annexation -
Project 7 LaGrange, Summerhill updated 12/18/08 |
Served |
Estimated
Start |
Estimated
Completion |
Estimated
Cost |
214 |
2009 |
TBD |
TBD |
Engineer
Design Firm: |
McKim
& Creed, P.A. |
Construction: |
TBD |
LaGrange, Summerhill Project Map (PDF Document)
PWC and its consulting engineers have begun the preliminary design process for installing water and sanitary sewer utility services in the LaGrange, Summerhill Areas. Survey crews with the consulting firms will begin site inspections and field surveys over the next several months.
| LaGrange, Summerhill Construction Schedule
There are 3 phases to construction: 1) street cutting and sewer installation; 2) street repair; and 3) restoration. |
||
| Street Name | Estimated Construction Date |
Status |