Annexation Phase V – Project 25 – Lake Rim Estates
Project Details
- Project 25 Map
- Design Start: March 2019
- Design Completion: October 2021
- Construction Start: April 2024
- Available for Connection: Spring 2026
- Services: Sewer – 245 | Water – 22
- Engineer Design Firm: Moorman, Kizer, and Reitzel
- Contractor: TA Loving Company
Communications
- Area 25- Meeting Handout (04/2024)
- Area 25- Construction Begins Letter (04/2024)
- Area 25_Construction Meeting Invite (03/2024)
- Construction Resolution- Project 25 (03/2020)
- Public Hearing Notice-Project 25 Preliminary Assessment (02/2020)
- Preliminary Assessment Resolution- Project 25 (12/2019)
- Project 25 Schedule (4/25/25):
Street Name | From | To | Estimated Construction Start Date | Status |
Rim Road Water Main | Ongoing | Crew installing 12″ water main along Rim Rd | ||
Castle Falls Circle | Rim Road | Rim Road | Ongoing | Mobilizing to Castle Falls Circle, beginning Sewer installation |
Tine Road | Rim Road | End | 4/28/2025 | Sewer Installation on Tine Road approaching the dead end. |
Oak Meadow Court | Rim Road | End | Ongoing | Clearing on easements Profile P. |
Rembrandt Drive | Ongoing | Crew moving fence on Rembrandt Drive. | ||
Gooden Drive | Rim Road | Skyline Drive | Ongoing | Sod installation for laterals and damaged areas. |
Holbrook Lane | Winterberry Drive | Kennesaw Drive | TBD | TBD |
Kennesaw Drive | Ongoing | Continuing grading and prepping site for sod installation. | ||
Mountain Home | Rim Road | Kennesaw Drive | 4/28/2025 | Completing Services on Mountain Home, Moving into Hollydale. Prepping and paving Mountain Home |
Winterberry Drive | Gooden Drive | Mountain Home Drive | Ongoing | Site preparation and paving operations, line testing. |
Hollydale Lane | Holbrook Lane | Mountain Home Drive | 5/4/2025 | Continuing sewer installation on Hollydale. |
Inglewood Lane | Holbrook Lane | Mountain Home Drive | Ongoing | Site preparation and paving operations. |
Profile B | Rim Road | Mountain Home Drive | Ongoing | Restoration, and pressure test on installed sewer lines. |
Profile C | Rim Road | Gooden Drive | Ongoing | Restoration, and pressure test on installed sewer lines. |
**Schedule is subject to change due to weather conditions and unforeseen delays.
The Construction Process
There are several phases to the construction process. PWC ensures that the Contractor makes every effort to limit interruptions and the impact on residents during each phase of the construction process. First, you will see design engineers and surveyors canvassing the area to determine the layout of the sewer collection system. Once the design is complete, the project will be bid and the construction phase will begin.
When construction begins, asphalt will be removed from the street and excavation crews will begin installing the sewer mains. This is typically done in one city block-sized area at a time. A second excavation crew will then install the laterals from the sanitary sewer main to the right of way. It will be the homeowner’s responsibility to connect from the clean out to the home once they are notified connections can begin.
Smaller excavations may be necessary throughout the construction process to test the lines and perform compaction testing to ensure the new asphalt does not fail. Once all excavation and testing have been completed, the contractor will then patch the asphalt and restoration will take place.
This information is subject to change.