FAYPWC.COM
FAYPWC.COM

Annexation Phase V – Project 25 – Lake Rim Estates

Project Details

  • Project 25 Map
  • Design Start: March 2019
  • Design Completion: October 2021
  • Construction Start: April 2024
  • Available for Connection: Spring 2026
  • Services: Sewer – 245 | Water – 22
  • Engineer Design Firm: Moorman, Kizer, and Reitzel
  • Contractor: TA Loving Company

Communications

Street NameFromToEstimated Construction
Start Date
Status
Rim Road Water Main  OngoingCrew installing 12″ water main along Rim Rd
Castle Falls CircleRim RoadRim RoadOngoingMobilizing to Castle Falls Circle, beginning Sewer installation
Tine RoadRim RoadEnd4/28/2025Sewer Installation on Tine Road approaching the dead
end.
Oak Meadow CourtRim RoadEndOngoingClearing on easements Profile P.
Rembrandt Drive  OngoingCrew moving fence on Rembrandt Drive.
Gooden DriveRim RoadSkyline DriveOngoing Sod installation for laterals and damaged areas.
Holbrook LaneWinterberry DriveKennesaw DriveTBDTBD
Kennesaw Drive  OngoingContinuing grading and prepping site for sod installation.
Mountain HomeRim RoadKennesaw Drive4/28/2025Completing Services on Mountain Home, Moving into
Hollydale. Prepping and paving Mountain Home
Winterberry DriveGooden DriveMountain Home DriveOngoingSite preparation and paving operations, line testing.
Hollydale LaneHolbrook LaneMountain Home Drive5/4/2025Continuing sewer installation on Hollydale.
Inglewood LaneHolbrook LaneMountain Home DriveOngoingSite preparation and paving operations.
Profile BRim RoadMountain Home DriveOngoingRestoration, and pressure test on installed sewer lines.
Profile CRim RoadGooden DriveOngoingRestoration, and pressure test on installed sewer lines.
*TBD: To Be Determined
**Schedule is subject to change due to weather conditions and unforeseen delays.

The Construction Process

There are several phases to the construction process. PWC ensures that the Contractor makes every effort to limit interruptions and the impact on residents during each phase of the construction process. First, you will see design engineers and surveyors canvassing the area to determine the layout of the sewer collection system. Once the design is complete, the project will be bid and the construction phase will begin.

When construction begins, asphalt will be removed from the street and excavation crews will begin installing the sewer mains. This is typically done in one city block-sized area at a time. A second excavation crew will then install the laterals from the sanitary sewer main to the right of way. It will be the homeowner’s responsibility to connect from the clean out to the home once they are notified connections can begin.

Smaller excavations may be necessary throughout the construction process to test the lines and perform compaction testing to ensure the new asphalt does not fail. Once all excavation and testing have been completed, the contractor will then patch the asphalt and restoration will take place.

This information is subject to change.