Annexation Phase V – Project 27 – Cliffdale Forest

Project Details

  • Project 27 Map
  • Design Start: April 2020
  • Design Completion: June 2022
  • Construction Start: March 2025
  • Construction Completion: March 2026
  • Available for Connection: Summer 2026
  • Services: 234
  • Engineer Design Firm: WK Dickson

Project Communications

Street NameEstimated Construction
Start Date
Status
Quailwood Drive6/30/2025Crew mobilizing and preparing for asphalt paving.
Patrick DriveOngoingContinuing sewer installation and setting manhole 72. Locating crew  locating existing utilities on Patrick Drive.
Week (7/7/2025) Crew building inverts and installing services.
Beverly Drive6/23/2025Remove and replace 6″ Aqua water main.
Week (7/7/2025) Crew mobilizing, cutting and preparing for asphalt paving.
Leslie Drive
From Leslie Drive to Patrick Drive
OngoingCrew cutting out and preparing for asphalt on Leslie Drive
Oakstone Drive
From Beverly Drive to Lowell Harris Road
OngoingCrew continuing sewer installation towards manhole 35.
Week (7/7/2025) Crew installing services.
Bridgette Street6/23/2025Crew mobilizing to Bridgette St to begin clearing ahead for Aerial Crossing.
Week (7/7/2025) Crew continuing clearing and haul off debris.

What You Need to Know About Planned Construction in Your Neighborhood

Click here for more information about the Annexation Construction Process

Click here for FAQ about the Annexation Construction Process


The Design Process

During the design process for this project area, engineers may visit with property owners. Once the design process has been completed, property owners will be notified by mail of the Preliminary Assessment Public Hearing held by the Fayetteville City Council that will begin the next phase of the project. 

This information is subject to change.