- Design Start: April 2020
- Design Completion: June 2022
- Construction Start: March 2025
- Construction Completion: March 2026
- Available for Connection: Summer 2026
- Services: 234
- Engineer Design Firm: WK Dickson
Project Communications
- Project 27 Construction Begins Letter (03/2025)
- Project 27 Construction Meeting Handout (03/2025)
- Project 27 Construction Meeting Invitation (03/2025)
- Project 27 Prelim. Assessment Letter (05/2021)
- Project 27 Prelim. Assessment Resolution (05/2021)
- Project Schedule is below as of June 19, 2025:
Street Name | Estimated Construction Start Date | Status |
Quailwood Drive | 6/30/2025 | Crew mobilizing and preparing for asphalt paving. |
Patrick Drive | Ongoing | Continuing sewer installation and setting manhole 72. Locating crew locating existing utilities on Patrick Drive. Week (7/7/2025) Crew building inverts and installing services. |
Beverly Drive | 6/23/2025 | Remove and replace 6″ Aqua water main. Week (7/7/2025) Crew mobilizing, cutting and preparing for asphalt paving. |
Leslie Drive From Leslie Drive to Patrick Drive | Ongoing | Crew cutting out and preparing for asphalt on Leslie Drive |
Oakstone Drive From Beverly Drive to Lowell Harris Road | Ongoing | Crew continuing sewer installation towards manhole 35. Week (7/7/2025) Crew installing services. |
Bridgette Street | 6/23/2025 | Crew mobilizing to Bridgette St to begin clearing ahead for Aerial Crossing. Week (7/7/2025) Crew continuing clearing and haul off debris. |
What You Need to Know About Planned Construction in Your Neighborhood
Click here for more information about the Annexation Construction Process
Click here for FAQ about the Annexation Construction Process
The Design Process
During the design process for this project area, engineers may visit with property owners. Once the design process has been completed, property owners will be notified by mail of the Preliminary Assessment Public Hearing held by the Fayetteville City Council that will begin the next phase of the project.
This information is subject to change.